CE Practice Question - Incorrect Answer?

Comments

3 comments

  • Avatar
    bowermb

    A change order would not be required for directing the reinstallation, as it does not affect the project budget, scope, or schedule.

    0
    Comment actions Permalink
  • Avatar
    Roman Buha

    Brett, thanks for your comment.

    Yes. I guess, even if the contractor would disagree to reinstall the materials, the architect still has the power to issue a Construction Directive together with the Owner. So the work will continue and the Change Order will be avoided until they will figure out who was right later(?).

    0
    Comment actions Permalink
  • Avatar
    bowermb

    Effectively, yes. It would potentially lead to arbitration (or whatever other method of dispute resolution is outlined in the contract) if the contractor insists additional money is owed.

    0
    Comment actions Permalink