ARE5 Practice Exam - Question 144
144. According to AIA Document A201, General Conditions of the Contract for Construction, the party responsible for determining the time limits for construction is the:
(A) owner
(B) contractor
(C) architect
(D) contractor and subcontractors
According to the book the correct answer is (D): contractor and subcontractors. However, when reading the solutions part, the first sentence says: "the owner is responsible for determining the time limits for construction".
I am almost certain that the correct answer is (A), the owner. I believe the book made a mistake. The contractor is just responsible for developing a construction schedule that allows construction within the owner's established time frame.
Any thoughts?
Thank you.