Ballast ARE 5 Review Manual Questions & BCI

Comments

5 comments

  • Avatar
    Yasmin Bazargan

    soley means only contractor and not other person (like architect, attorney, ....)

    claims of subs (attorney can review)

    field report to owner (architect does too)

    selection of subs (sometimes architect and owner dont like a specific sub and give their input to contractor)

    scaffolding is 100% related to contractor only 

    1
    Comment actions Permalink
  • Avatar
    Peter Mall (Edited )

    Example 50.3: the correct answer is A) field reports to owner

    Note: the answer stated as "C) Scaffolding" is a typo which appears on earlier publications of Ballast and has been updated since.

    Edit: Scaffolding is part of the means of construction, which is the contractor's responsibility. Field Reports are the responsibility of the architect. Selection of subcontractors is subject to the approval of both the architect and the owner. If a subcontractor makes a claim to the contractor, the contractor in turn makes a claim to the owner that is reviewed by the architect.

    0
    Comment actions Permalink
  • Avatar
    Juan Fable

    Thank you Yasmin and Peter for the responses. these are helpful, I was trying to find the 'addenda' for this Ballast but couldn't find it. Do you happen to know where I can find those?

    0
    Comment actions Permalink
  • Avatar
    Yijun Wu

    I believe the 50.3 question should erase "NOT" and the correct answer can be scaffolding, which is solely contractor's responsibility.

    2
    Comment actions Permalink
  • Avatar
    ccamuz (Edited )

    I've also noticed the error in Example 51-1. Correct answer should be
    C) Contractor

    A201_General Conditions for the Contract for Construction

    § 9.8 Substantial Completion
    § 9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of items to be completed or corrected prior to final payment.  Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.  
    § 9.8.3 Upon receipt of the Contractor's list, the Architect will make an inspection to determine whether the Work or designated portion thereof is substantially complete. If the Architect's inspection discloses any item, whether or not included on the Contractor's list, which is not sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Architect. In such case, the Contractor shall then submit a request for another inspection by the Architect to determine Substantial Completion.

     

    A295_General Conditions of the Contract for IPD

    ARTICLE 10 CLOSEOUT PHASE
    § 10.1 PROJECT COMPLETION
    § 10.1.3 The Architect's inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the GMP Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
    § 10.1.4 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of items to be completed or corrected prior to final payment. Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the GMP Documents.
    § 10.1.5 Upon receipt of the Contractor's list, the Architect will make an inspection to determine whether the Work or designated portion thereof is substantially complete. If the Architect's inspection discloses any item, whether or not included on the Contractor's list, which is not sufficiently complete in accordance with the GMP Documents so that the Owner can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Architect. In such case, the Contractor shall then submit a request for another inspection by the Architect to determine Substantial Completion.

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk