NCARB PRACTICE EXAM QUESTION - MASTER FORMAT RELATED

Comments

7 comments

  • Avatar
    abruno168

    Process of elimination works best here. The main point is that the options are released in conjunction with the wall insulation bid package, meaning the work will be completed congruently.

    Option A refers to flashing and sealants, which wouldn't apply for interior stud furring. Option C would be after the insulation, interior cavity routing, and stud installation is complete. Option B is separate insulation treatment for applications that aren't related to the insulated wall assembly.

    Option D is correct due to the sequence of construction and assembly, as the answer explains.

    2
    Comment actions Permalink
  • Avatar
    JCorrington

    Yep process of elimination. Ask yourself which one of these things goes inside a wall? There is only one answer, D.

    2
    Comment actions Permalink
  • Avatar
    Henry T

    abruno168, thank you for the detailed explanation with the highlight on key word conjunction with the bid package.
    I may have also missed the very important hint that it is fast-tracked. Which would mean that option C is theoretically correct, but at a later time, in another bid.

    2
    Comment actions Permalink
  • Avatar
    Professor Hanlon (Edited )

    Henry:

    We offer live online lectures on this exam beginning Nov 1, 2025. Please join us.

    Professor Hanlon

    -2
    Comment actions Permalink
  • Avatar
    Ralph Hale

    Hi Henry, 

    Fast-tracked doesn't really matter here - the keys are typical construction sequence things, and what goes where basically - as JCorrington and abruno said.  C. specifically is the spec for Interior Painting - it comes well after insulation would, and so doesn't need to be released with the insulation bid package.  Starting with that the wall was supposed to be insulated but isn't, so insulation is being added in the stud bays that are being added as furring against the block wall. I can't really come up with a scenario where interior painting would need to be released congruently with insulation work.

    You're looking for something that should really happen before the insulation is installed.

    In normative construction, wiring and electrical boxes are run within the wall - where there is block with furring, it's run in the depth of the furring. 

    The other further hint that it is the electrical boxes is the type of insulation - spray foam is much more difficult to modify after the fact - in almost all cases you want to install insulation after electrical and plumbing work - really anything being run in the walls - is complete. 

    Happy studying!
    Ralph, the Amber Book Team


    2
    Comment actions Permalink
  • Avatar
    Henry T

    That is the perfect explanation for this question.

    Thank you, Ralph.

    1
    Comment actions Permalink
  • Avatar
    Ralph Hale

    Welcome!  Glad it was useful to you.  

    Cheers,
    Ralph, the Amber Book Team

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk