Schedule of Values - If not using a GMP or Stipulated Sum contract?
Hello,
What if your're an Architect working on a project that is very large using a (Cost + Plus Fee with out a GMP) delivery method. This delivery method does not require the use of a Schedule of Values when working with the General Contractor to complete Application for Payments. Does anyone know what the Architect would do in this scenario?
Thank you for your help.
-
The architect would just verify the actual construction costs. And then add the % fee. It would be much simpler than trying to check the schedule of values and verifying that the contractor has completed 50% of the work, and if they are billing for 50%.
The only 'trick' would be making sure that the owner isn't paying for any items that are not included in the contract.
Hope this helps!