Question about AHPP 15th Edition, Page 637
There is a section that reads as follows:
Compensation/Planned Cost = Planned Multiplier
$1,025,000/$334,778 = 3.06
-$64,425 x 3.06 = $197,141
Where did the $334,778 amount come from? I’m seeing that planned labor is $335,981 on the summary tab on the same page.