Contractor submits during presconstruction phase
What should the contractor submit to the owner, through the architect, during the preconstruction phase of a traditional design-bid-build project
-
- Insurance Certificate
- Bid bond
- Performance bond
All are part of contracting Requirements under Project Forms for DBB.
Schedule of value will be submitted by the GC to the Arch prior to the first application of payment (A201 # 9.2)
Proof of financial will be submitted by the owner to the GC upon request of GC (A201 # 2.2.2)