    Rebekka O'Melia

    Yuan,

    This is correct.  The other 3 items relate to quality control, not the time factor.

    What is your question??

    It's very easy to spend too much time on something if nobody is watching the timesheets and looking at the project's progress.

    Hope this helps!

    Rebekka O'Melia, Registered Architect, NCARB, B. Arch, M. Ed, Step UP,  Step UP ARE 5.0 Courses

    0
    Comment actions Permalink
  • Avatar
    Yuan Ma

    Hi Rebekka,

    Thank you for your answer. My question is why is B not correct?

    0
    Comment actions Permalink
  • Avatar
    Rebekka O'Melia

    Hi Yuan,

    I think B is not correct because the milestones could be completed either UNDER the budgeted hours or OVER the budgeted hours.  Being profitable is about keeping track of time and resources spent and making sure the hours stay within the project budget. 

    If the question asked only about the schedule or quality control, then a checklist for milestones for SD, DD and CDs would be appropriate.

    Hope this helps & keep studying!

    Rebekka O'Melia, Registered Architect, NCARB, B. Arch, M. Ed, Step UP,  Step UP ARE 5.0 Courses

     

     