Commissioning ARE sample question #1
Which of the following can be found in a commissioning report? (Check the three that apply.)
- Steel beams
- MERV-13
- Rain sensors
- Water heaters
- TPO roofing
Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)
-
Response: 2, 3, and 4. A commissioning report typically include items related to mechanical, plumbing, electrical and irrigation systems. Steel beams are part of the structural system, TPO roofing is a part of architectural system and they are NOT included in the commissioning report.
MERV-13 is a filter typically required in a mechanical system, rain sensors are part of the irrigation system, water heaters are part of the plumbing system. They are included in the commissioning report.
Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)