    Hi Kati:

    The General (and Supplemental) conditions are part of the Project Manual, but the Specs start with Division 01.  Division 00 comprises procurement and contracting requirements.  The General Conditions (A201) do not get modified (or signed).  The typical conditions are in the A201.  You should definitely read it, if you haven't already.  If there are owner specific conditions (let's say the owner wants to pay monthly on the 8th of the month instead of the 1st or something odd), then a Supplementary Conditions doc gets added to the contract conditions.

    The specs are divisions 1-49.

    Hope this helps!

    Rebekka O'Melia, Registered Architect, NCARB, B. Arch, M. Ed, Step UP,  Step UP ARE 5.0 Courses

     