The party responsible for determining the limits for construction?

Comments

1 comment

  • Avatar
    Rebekka O'Melia

    The Owner-Contractor agreement, the A101, would outline the project start date, and the target date for substantial completion.  The owner can be required to extend these days based on factors like the weather or availability of construction materials.  So the sub does not DIRECTLY change the construction schedule, you are correct.  But the sub may say to the GC, "I cannot get any tile that would meet the project requirements in the required time frame, so we need to push out the schedule X number of days...".

    I think that answer is (partially) correct, the explanation may need to be more detailed though.

    Hope this helps!  Keep studying!

    Rebekka O'Melia, Registered Architect, NCARB, B. Arch, M. Ed, Step UP,  Step UP ARE 5.0 Courses

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk