Who can order a contractor to pick a new subcontractor?

Comments

2 comments

  • Avatar
    Gang Chen (Edited )

    Here is the official A201, 5.2.3 language about this, the objection has to be reasonable, and the contractor may ask for a change order:

    Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)

    0
    Comment actions Permalink
  • Avatar
    Kirill Ryadchenko (Edited )

    I have a follow-up question. 
    What if the Owner or Architect wants the Subcontractor fired from the job after a 14-day period of notice for reasonable objection expired and the Subcontractor already started Work. I couldn't find any provision for such action in A201. Can the Owner or Architect request to change Subcontractor after the window for objection expired and the Subcontractor started the work?