Differences between required closeout documents for contractor

Comments

1 comment

  • Avatar
    abruno168

    The question is asking what record documents must the contractor provide to the architect for review.

    Record documents would be used to capture the as-built conditions and modifications made to the original drawing set and bound contract documents issued as part of the contract. Payment applications, punch list, and addenda would not be part of record documents that capture these changes. Change orders capture the scope and cost of changes, supplemental drawings make up the gap between the IFC set and the change directives given, and submittals catalog the relevant products being specified and used.

    1
    Comment actions Permalink

Please sign in to leave a comment.