According to AHPP page 526 :
"Fast track is a method of delivery that allows AE documents to be issued in multiple stage, or bid package."
Do I understand it correctly: is this means that Fast Track is not a delivery method for construction work (which I know that is not). I am confused.
Please confirm.
Thank you.
Izabela
-
That sentence is confusing.... :(
I think Fast track essentially is an approach to speed up construction by overlapping phases(start to build one part of the project while the remaining parts are still being designed or drawn up).
I have seen other study materials refer fast track as a delivery method, but if you think about it, a fast track process/approach can be applied to Design-Bid-Build, Design/Build, or CM@R .
Hope this helps. -
This sentence is confusing. Fast tract is a project delivery method that affects both design and construction.
Gang Chen, Author, Architect, LEED AP BD+C (GreenExamEducation.com)