Scheduling Question - Please advise !
the question is : in order to stay on schedule ,the excavation shall take no longer than how many days ?
i am confused as to whether we will us calendar days or business days here and if we can extend the excavation to the time the conc ends because this still wont affect the task after ( which is steel )
if possible dont explain it relative to the actual work on site because the question can be about something else on the exam - just need to understand how to read the chart
-
Sandy, I suppose the short answer is 7 days. These charts are read in calendar days (not business days) for simplicity. If the schedule says excavation will take 1 week, than you should assume 7 days. Anything further may throw off the concrete (foundation) from being poured.
Ben | Archizam