Scheduling Question - Please advise !

Comments

1 comment

  • Avatar
    Benjamin Eckhard

    Sandy, I suppose the short answer is 7 days. These charts are read in calendar days (not business days) for simplicity. If the schedule says excavation will take 1 week, than you should assume 7 days. Anything further may throw off the concrete (foundation) from being poured.

    Ben | Archizam

    0