Ballast CE Practice Help - Critical Path Schedule
11. The architect is reviewing a critical path method schedule from the contractor. The critical path is 200 calendar days with 30 days of float. Contractor plans on 5 day work week. What is the construction time?
Ballast says divide 200 calendar days by 5 working day to get about 40 weeks for construction. But if the project will take 200 calendar days wouldn't you divide by 7 for the days in a week resulting in approximately 28 weeks? 40 weeks for construction would be more than 200 calendar days. Is this just a Ballast typo or am I missing something?
Thanks!
-
It is probably a typo.
Gang Chen, Author, Architect, LEED AP BD+C (GreenExamEducation.com)
Please sign in to leave a comment.
Comments
3 comments