Ballast CE Practice Help - Critical Path Schedule

Comments

4 comments

  • Avatar
    Gang Chen (Edited )

    It is probably a typo.

    Gang Chen, Author, Architect, LEED AP BD+C (GreenExamEducation.com)

    0
    Comment actions Permalink
  • Avatar
    Hans-Christian Karlberg

    Hi Samantha. In the second edition of Ballast practice questions it says "The critical path is 200 days" - that's total days and not calendar days. Meaning that you divide 200 by 5. (=40 weeks of construction time) It could in fact have been a typo that they corrected in the latest edition. Now you're going to ask me about the weekends, and if they count towards total time. The questions asks for "construction time". The multiple choice options are 40weeks, 46weeks, 32weeks and 6weeks.

    One of my qualms with NCARB questions is that they often provide superfluous information, which steals valuable time away from the examinee. 

    0
    Comment actions Permalink
  • Avatar
    Samantha Marie Fernholz

    I'm not surprised by a Ballast typo, but that clears it up. Thanks! 

    0
    Comment actions Permalink
  • Avatar
    Rebekka O'Melia

    Contractors do not work on the weekends typically, unless they are paid extra.  200 days = 40 weeks.  The work week is 5 days.

    Makes sense?

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk