Ballast CE Practice Help - Critical Path Schedule

Comments

3 comments

  • Avatar
    Gang Chen (Edited )

    It is probably a typo.

    Gang Chen, Author, Architect, LEED AP BD+C (GreenExamEducation.com)

    0
    Comment actions Permalink
  • Avatar
    Samantha Marie Fernholz

    I'm not surprised by a Ballast typo, but that clears it up. Thanks! 

    0
    Comment actions Permalink
  • Avatar
    Rebekka O'Melia

    Contractors do not work on the weekends typically, unless they are paid extra.  200 days = 40 weeks.  The work week is 5 days.

    Makes sense?

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk