ARE 5.0 Handbook PjM problem

Comments

3 comments

  • Avatar
    Nick NCARB

    Hey Valerie,

    I am happy to help but am not totally sure what you are asking. Can you clarify your questions on this PjM Handbook item?

    0
    Comment actions Permalink
  • Avatar
    Sebastian Garcia

    Just means 40 hours a week (per person) as opposed to like ... 50, which would infer overtime..

    0
    Comment actions Permalink
  • Avatar
    Adele Salierno

    Hi Valerie,

    The solution is 110 hours/week for all the 4 members of the team combined (not 110 hors/week for each onr of them).

    I hope this helps!

    0
    Comment actions Permalink