AHPP Figure 10.12
Is anyone else having a hard time understanding where the Planned Cost of $334,778 is coming from? The planned Labor cost on Figure 10.12 is $335,981, but when calculating the Planned multiplier, the book uses $1,025,000/$334,778.
-
Hi. Could you post a pic of this Luis? Then I can help.
Thanks!
Rebekka O'Melia, Registered Architect, NCARB, B. Arch, M. Ed, Step UP, Step UP ARE 5.0 Courses
-
Hey, did you ever get this figured out? I have no idea where they are pulling the compensation figure of $1,025,000 or the planned cost figure of $334,778 from. Neither figures are included in the table.
This is on page 637 of AHPP
Rebekka O'Melia