Retainage Payment and Article 9.8.5 in AIA A201

Comments

2 comments

  • Avatar
    Dylan Lopez

    Correct if the project and contract call for retainage they release retainage after substantial completion and usually try to hold back at least twice the cost of the punch list work. 

    0
    Comment actions Permalink
  • Avatar
    Kevin Griendling

    For the sake of clarity for other candidates using this board, I would like to add that this is a sub-section under "9.8 Substantial Completion". That would be the 'WHY' it is substantial completion and not any other milestone.

     

    Good luck,

     

    Kevin Griendling, AIA

    http://xQ.intersectartsstudio.com 

    http://www.pluralsight.com 

    0
    Comment actions Permalink