Ballast Example 5-2 - answer???

Comments

2 comments

  • Avatar
    Inda Sechzer

    I see I am wrong.  A CO is included in modifications.  Thanks!

    0
    Comment actions Permalink
  • Avatar
    David Kaplan

    Inda,

    A good thing to remember is that the Contract Documents don't "end" at the signing of the contract.  Think about this: what if a job is design-build and the construction contract is signed at day one of the project?  That could be the case in some instances, not all.  

    Changes to the drawings (Addenda and Bulletins) are part of the Contract Documents, which is why CO's are included as well.  Don't let the word "Contract" in "Contract Documents" throw you off.  Hope that helps.