Tests and Inspections B101 vs A201

Comments

2 comments

  • Avatar
    Neha Sadruddin

    That's correct. In B201 since the contractor is not in the picture yet, the owner is responsible for paying for all tests and inspections. I believe the tests referred to in A201 are related to construction like concrete slump test etc. So those would fall under the contractor's responsibility. Any additional tests that are required but not made clear before bidding will also be paid for by the owner since the contractor has not accounted for them in his bid. 

     

    Hope this helps!

  • Avatar
    Herman Nadal

    Thanks, Neha! That helps.