(September 4, 2025 @ 6pm ET) 40 Minutes of Competence PjM Study Session: The Art of Project Planning - I Gantt Believe We’re Behind Schedule
This week's Amber Book : 40 Minutes of Competence program is titled, “The Art of Project Planning: I Gantt Believe We’re Behind Schedule”
Relevant Exam Division: Project Management (PjM)
These study sessions are free and open to all, not just Amber Book subscribers, so join us this Thursday at 6pm ET: https://us02web.zoom.us/j/83922907346
You’ll take the first five minutes of class to answer this week's question alone, but if you would like to get a head-start on that, here is the assignment:
The dependency relationship of the “Construction Process” task and the “Marking the Layout” task can best be described as _______.
a. Start-to-start
b. Start-to-finish
c. Finish-to-start
d. Finish-to-finish
(To see a larger version of the above image, click here)