Allowance

Comments

1 comment

  • Avatar
    abruno168

    Options C and D would be the same regardless of the signage selected, as A201 3.8.2 states that allowances will cover cost of materials and equipment delivery, and cost for labor, overhead, install, profit, etc. Option B also would not be considered because the architect is the one who prepares the change orders to be processed.