(June 26, 2025 @ 6pm ET) 40 Minutes of Competence Study Session: Navigating Project Closeout
This week's Amber Book : 40 Minutes of Competence program is titled, “Navigating Project Closeout”
These study sessions are free and open to all, not just Amber Book subscribers, so join us this Thursday at 6pm ET: https://us02web.zoom.us/j/83922907346
You’ll take the first five minutes of class to answer this week's question alone, but if you would like to get a head-start on that, here is the assignment:
As a project approaches completion, here are the remaining steps:
1. Punch list items corrected
2. Substantial Completion declared
3. Owner announces final completion
4. Punch list made
5. Correction-of-Work period commences
6. Architect approves final paymentWhich of the following arranges these steps in the most correct sequence?
a. 4, 2, 5, 1, 6, 3
b. 2, 4, 1, 5, 6, 3
c. 4, 3, 1, 6, 5, 2