    1,080,000 is the total design fee based on the 6% of max construction cost of 18M. 

    The RFP outlines that 20% of the total design fee (not the fee after CSME's fee is considered) is to be attributed to women/minority owned businesses, that being ABC Architects as the design consultant. 35% of the total design fee is attributed to CSME per the question/information provided. The take home fee for XYZ is based on the total design fee deducted by the engineering and design consultant fees.

    1,080,000 - 378,000 [CSME 35% of total design fee] - 216,000 [ABC 20% of total design fee] = 486,000 XYZ fee