Two days prior to the bid due date, a major conflict is discovered in the bid documents between the architectural and structural drawings. The conflict will require extensive reworking of the drawings and additional structural steel.
What should the architect issue to bidders?
The answer is Addendum that defines the changes and extends the bid due date.
However I was under the impression that according to A701 that the last day to issue addenda is no later than 4 days piror to the date for receipt of bids?