CE CASE STUDY Scenario Architect's Field Report
I chose A as my answer, but I would like some additional clarification on this problem.
Is the correct answer determined by the distinction between "Direct" vs. "Recommend", or is it based on the statement:
"The G702-1992 pay application shows a $10,000 fee for the sheet vinyl work completed. – Case Study Attached Document"?
Both A and B seem similar, but I chose A because it aligns with:
"The Architect has the authority to reject Work that does not conform to the Contract Documents. – AIA 201 4.2.6."
I’d appreciate any further guidance on this.
Thank you!
-
Hello,
Looking at this question in isolation.
Because there is no contractual relationship between architect and contractor, architect cannot tell contractors to suspend construction. A will assume extra responsibility on the architect.
"Rejecting non-conforming work" won't happen in this stage because the cause isn't clear.
Hope this helps.
Please sign in to leave a comment.