Elevator Question

Comments

7 comments

  • Avatar
    ayanohosoda

    Wow... I just asked this question to ChatGPT, and I got this response. Is this correct?

     

     

     

    Great question! The reason architects are not responsible for shaft and pit dimensions during the elevator submittal review is because these dimensions are primarily dictated by the elevator manufacturer and structural engineers, rather than the architect. Here’s why:

    1. Manufacturer’s Responsibility

    Elevator shaft and pit dimensions must comply with the specific requirements of the elevator system being installed. Elevator manufacturers provide precise specifications based on their equipment, which include:

    • Shaft width and depth
    • Pit depth
    • Overhead clearance
    • Door openings and tolerances

    Since these specifications vary between manufacturers and models, architects typically design the shaft based on preliminary manufacturer data, but the final dimensions are verified by the elevator contractor.

    2. Structural and Code Compliance

    • Structural engineers ensure the shaft and pit can support loads, seismic forces, and reinforcement needed for the elevator system.
    • Building codes (e.g., IBC, ADA, ASME A17.1) have strict requirements for clearances, emergency access, and safety features, which the elevator contractor and structural team must verify.
    • Architects coordinate the general layout but do not take responsibility for the precise shaft and pit dimensions, as those are dictated by elevator shop drawings and the manufacturer’s guidelines.

    3. Shop Drawing Review vs. Design Responsibility

    When reviewing elevator submittals, architects primarily check for coordination issues (e.g., door alignments, aesthetic integration) rather than structural dimensions. The elevator contractor ensures final measurements comply with their system, and any discrepancies are resolved between the structural engineer, general contractor, and elevator supplier.

    Conclusion

    Architects design the space for the elevator, but do not finalize the shaft and pit dimensions because:
    ✔️ These are manufacturer-specific requirements.
    ✔️ The structural team is responsible for ensuring the shaft/pit can withstand forces.
    ✔️ The elevator contractor is responsible for precise measurements and installation compliance.

    Let me know if you need further clarification! 😊

    0
    Comment actions Permalink
  • Avatar
    ynigen

    The short answer is that for submittals, the contractor is always the first to review it and is responsible for the dimensions. The architect, however, is responsible for reviewing the design intent, such as finishes, materials, and aesthetics. If the architect notices that something is off, then the architect could contact the contractor to clarify, but we are not responsible for dimensions. 

    Submittal- contractor reviews and ensures that the information aligns as per the drawings/contract documents. The architect ensures that the design intent is being reached. For example, proper equipment was specified, correct paint colors referenced, and correct finish materials and suppliers are specified.

    0
    Comment actions Permalink
  • Avatar
    ayanohosoda

    I see. Thank you for the clarification!

    0
    Comment actions Permalink
  • Avatar
    rebekkak

    This is a good question.  Another thing to remember is that the shaft walls are built before the elevator is installed.  They are usually masonry or other fire rated material, built free standing.  We may have drawn the elevator shaft as 4'-0" x 6'-0" let's say, but in the field it may not be exact.  The elevator rep would come out and measure.  Realistically, it could be 3'-10" x 6'-0 -1/2" or something.  It would not be our position to give these actual dimensions to the elevator company during construction or check them on the submittal.

    However, we definitely would have sized this elevator and selected the type of elevator based on the # of occupants of the building, and the type of building, and its height.  We also would have designed the lobby dimensions.

    Hope this clarifies it for you!  I think that answer is 100% correct.

    Rebekka Klos, NCARB, B. Arch, M. Ed, ARE Educator

    www.stepuparchitecture.com

    0
    Comment actions Permalink
  • Avatar
    ayanohosoda

    I totally get it now! Thanks you so much!!

    0
    Comment actions Permalink
  • Avatar
    celinehaddad

    Why wouldn't the "hydraulic pump equipment" answer be selected, if the architect is also verifying the machine room controller? 

    0
    Comment actions Permalink
  • Avatar
    scantando

    celinehaddad it might be a trick answer of sorts as the type of elevator used in a high rise is a cable elevator and therefore does not have a hydraulic pump.  

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk