CE Exam Practice Question Blitz: Zoom Study Session
Thursday's 09/05 free 6pm ET Zoom study session is titled, “An Expert’s Process for Answering ARE Questions: CE Exam” Preview the question we’ll be covering below.
Find the Zoom link here: https://us02web.zoom.us/j/83922907346
A four-story, wood-framed multifamily residential building is nearing completion and the contractor requests a certificate of substantial completion. Following a site observation visit, the project architect prepares a punch list describing items observed that will need to be corrected.
Which punch list items require correction before the architect can certify substantial completion? Check the three that apply.
A. Stair 5, Typ. All Levels: Missing handrails along east wall of staircase
B. Corridor Lobby, Level 1: Replace flickering light in accent fixture
C. Corridor, Level 3: Add missing lock on fire extinguisher cabinet
D. Unit 123 (1 bed/1 bath): Replace toilet in bathroom (will not flush)
E. Unit 325 (2 bed/2 bath): Missing smoke detector in bedroom
F. Unit 424 (1 bed/1.5 bath): Missing screen at sliding balcony door