An Expert's Process for Answering ARE Questions: Part 3 - Zoom Study Session
Thursday's 06/13 free 6pm ET Zoom study session is titled, “An Expert's Process for Answering ARE Questions: Part 3”
Preview the question we’ll be covering below.
Find the Zoom link here: https://us02web.zoom.us/j/83922907346
An architect notices a conflict between a two-inch sanitary line and a structural beam. The beam is a W24 steel wide flange with one end supported by a steel girder and the other end supported by a concrete wall. The architect wants to disturb the structural system as little as possible. Where should the architect detail the beam penetration?
- Web opening at the beam quarter span.
- Web opening at the beam middle span.
- Web opening at the end of the beam.
Please sign in to leave a comment.