PcM mock exam Q10

Comments

12 comments

  • Avatar
    Katerina Buscemi

    Was this from the ncarb practice test? I agree that the answer should be C, although I suppose it calls into question the meaning of efficiency. Any time the contractor’s profit is guaranteed, they are less encouraged to seek the best pricing but why should cost plus cause them to wrap the project up quicker than stipulated sum?

    0
    Comment actions Permalink
  • Avatar
    Morgan Subramanya-Iyer Raman

    Stipulated Sum assumes a full set of contract documents that are complete, or at least sufficient to describe the scope of work being purchased by the owner at the time of entering into the agreement and to set a fixed price for that fixed scope of work. In practice, it is not that simple.

    Cost Plus is used when construction has to begin before all the drawings are done (this happens more frequently in practice), the contractor may charge the owner for the actual costs of labor, materials and sub-contractors, adding overhead and profit either as an agreed-upon percentage of the costs to be reimbursed or as a fixed amount. 

    What ends up happening in Stipulated Sum is that, if the contractor makes money on the job, the owner cannot ask for a refund.  Conversely, if the contractor loses money on the job, the owner cannot be billed for more.

    So, A is the answer. 

    2
    Comment actions Permalink
  • Avatar
    Katerina Buscemi

    Thank you for that explanation, Morgan. That does make some sense but it doesn’t really define efficiency as finishing the job earlier. Does starting construction earlier make it more efficient? Are there not instances where cost plus is used after CDs are complete? For instance in the case where quality is the number one driver? The question asks us to make a lot of assumptions

    0
    Comment actions Permalink
  • Avatar
    Katerina Buscemi

    I guess if I were to define efficiency for myself it would be a productive use of time and resources. Unless the contractor’s profit is tied to a productive use of time, I don’t see how cost plus is ever more efficient.

    0
    Comment actions Permalink
  • Avatar
    Ruby Jean Cruz

    Thank you for your responses!
    This question is from the ARE 5.0 Mock Exam by Ballast.
    I had the same thoughts with you Katerina. I think it boils down to the more accurate definition of efficiency. I also thought that it should be cost and time but if it is quality work done in a shorter time, it may be A.

    The book’s explanation was similar to Morgan’s explanation which makes me assume a few things/additional factors that were not in the question, which I try to avoid. I agree that in most situations, cost plus is used more than stipulated sum.

    1
    Comment actions Permalink
  • Avatar
    Katerina Buscemi (Edited )

    Oh I’m relieved to hear it was from ballast and not on the ncarb practice exam. Ballast is often filled with these types of inconsistencies. I’d take these kinds of answers with a grain of salt. Thank you for clarifying because I was in panic mode - my test is in two days 😅

    0
    Comment actions Permalink
  • Avatar
    Ruby Jean Cruz

    That’s good to know! I have a few other questions that I needed further explanation like this… It takes me a LOT of time to try to understand.

    My exam is in 4days! I guess I need more reliable practice exams aside from NCARB Practice exam. Do you have any other recommendations?

    0
    Comment actions Permalink
  • Avatar
    Katerina Buscemi

    Have you tried the Amber book questions? S bit difficult to get last minute unfortunately. I’ve heard Elif’s ARE questions are good and also hyperfine. Sorry I can’t be more help! But feel free to post any questions you’re unsure about. I’m just rereading chapter 9 of AHPP now covering project delivery methods

    0
    Comment actions Permalink
  • Avatar
    Ruby Jean Cruz

    Thank you!!!

    Ive been contemplating on getting Elif. Ive heard of it numerous times. I’ll try that one. Thanks and good luck on your exam! 😊

    0
    Comment actions Permalink
  • Avatar
    Katerina Buscemi

    Yes, I thought about purchasing them myself but had trouble signing up for an account from my phone! I’m going to spend all day tomorrow reviewing test questions if you want to reach out to me on instagram I'm @katerinabuscemi

    0
    Comment actions Permalink
  • Avatar
    Karim Yussuf

    How did you both do? I had an exam on the same day too, but wasn't the best experience for me..

    0
    Comment actions Permalink
  • Avatar
    Katerina Buscemi

    Hi Karim, I’m sorry about your experience. The provisional feedback was “likely pass” but I have to say I also felt the test was horrible, especially the use of tricky language. I was so nervous I wouldn’t finish. Praying I can rely on the “likely pass” as I never want to do that again

    1
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk