CE. For NCARB Question Developers

Comments

3 comments

  • Avatar
    NCARB

    Hello Fedor.

    This item has been flagged and will be reviewed and revised as part of our update to practice exam at the end of February.

    1
    Comment actions Permalink
  • Avatar
    Clayton Artz

    Fedor,

    When calculating 90% (work completed “This Period” + “Materials Presently Stored”), shouldn’t you exclude $21,073 for Sitework since retainage is no longer being collected once the Description of Work has reached 90%? It doesn’t make sense for the Owner to pay back the Contractor for all retainage from Sitework, but still collect 10% in retainage for Sitework completed this period. The question doesn’t tell us the specifics of agreement, but I would assume once the line item hits 90% completion and the Owner releases all retainage for this item, the retainage would stop all together for this line item for remainder of construction.

    My Calculation:

    1. 161,565 - 21,073 = 140,492
    2. 140,492 + 37,940 = 178,432
    3. 178,432 x 0.9 = 160,588.80
    4. 160,588.80 + 21,073 = 181,661.80 (Sitework completed “This Period” is added back on with no retainage)
    5. 181,661.80 + 11,348.30 = 193,010.10

    0
    Comment actions Permalink
  • Avatar
    Fedor Frolov

    Hello. 
    Take a look on retainage column in table. Its amount for sitework item equals 11,348.30 which is 10% of 113,483 which is the sum of 21,073 and 92,410. So to have a 11,348 retainage you should also retain 10% of 21,073.

    0
    Comment actions Permalink