CE. For NCARB Question Developers
Hello.
Please check CE Test Question for discrepancy.
Considering the Thoughts and logic in attached document.
Thank you.
-
Fedor,
When calculating 90% (work completed “This Period” + “Materials Presently Stored”), shouldn’t you exclude $21,073 for Sitework since retainage is no longer being collected once the Description of Work has reached 90%? It doesn’t make sense for the Owner to pay back the Contractor for all retainage from Sitework, but still collect 10% in retainage for Sitework completed this period. The question doesn’t tell us the specifics of agreement, but I would assume once the line item hits 90% completion and the Owner releases all retainage for this item, the retainage would stop all together for this line item for remainder of construction.
My Calculation:
1. 161,565 - 21,073 = 140,492
2. 140,492 + 37,940 = 178,432
3. 178,432 x 0.9 = 160,588.80
4. 160,588.80 + 21,073 = 181,661.80 (Sitework completed “This Period” is added back on with no retainage)
5. 181,661.80 + 11,348.30 = 193,010.10
Please sign in to leave a comment.