CE Mock up exam question - retainage

Comments

3 comments

  • Avatar
    Blane Hammerlund

    The question says, if 90% of the work is completed then the Retainer can be released (which is the case for the site work or line item 1). So it is the monthly charge plus the charge for the materials currently stored plus the Retainer for the site work because the site work is at 90%. The sum of those 3 things gives you the correct answer.

    0
    Comment actions Permalink
  • Avatar
    Russ Montenero (Edited )

    I often see in the A101 that retainage is not held for site work nor stored materials/offsite stored materials, but it must be made clear in the 101 to do so. 

    0
    Comment actions Permalink
  • Avatar
    Akram Tawfic

    Adding the total completed and the balance to finish

    you'll get the scheduled value, so you can easily notice that retainage subtract 

    and if you need to complete form G-702 you'll get deduct the retainage value of item 1

    that form it correct in comply with form G-702 yet the question is confusing and the answer too 

    could someone help me to recognize and connect the numbers here?

     

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk