Can someone explain this PjM scheduling example in the ARE 5.0 Handbook?

Comments

2 comments

  • Avatar
    Lizjaira Concepción Navedo

    If permitting is delayed by 3 weeks construction will also be delayed 3 weeks as it can not begin until the permits are acquired. On top of that construction in its self is also delayed as you need to add another 3 weeks to finish the work, for a total of 6 weeks delay. The 2 weeks delay in bidding has no effect on the schedule as it is less than the three weeks delay for permitting and these are tasks that happen simultaneously. 

    Hope this helps! 

    0
    Comment actions Permalink
  • Avatar
    Christopher Boucher

    Yes I understand now! Thanks!