    The CMC would send the Application for Payment to the Architect.  The architect checks it over.  If everything matches the schedule of values, and the work completed matches the cds, the architect forwards the app to the owner.  

    The owner ultimately pays for everything, and they are the only party left after the building is completed.

    Rebekka O'Melia, B.Arch, M. Ed, Registered Architect, NCARB,  Step Up ARE Prep