does cost of change order include GC's overhead and profit?

Comments

10 comments

  • Avatar
    David Kaplan

    Rubi,

    Admittedly I'm a little confused by the answer myself so I'll let others chime in on whether or not overhead and profit should be included (which I gotta tell you, I sure as hell thought that answer was "yes - it should be included" but according the what you are saying the correct answer is here, it is not).  I wanted to offer to you though that the AIA Contract portion you have provided is for allowances, not Change Orders. Different thing.  you are referring to the wrong part of the AIA Contract.  Allowances are not Change Orders.  Allowances are a set amount of money that one includes in a bid for an item whose quantity and/or design is to be included in the job but is not finalized in the drawings.  One example could be door hardware.

    0
    Comment actions Permalink
  • Avatar
    Rubi Xu (Edited )

    David Kaplan the allowence part of A201 i refered is actually for the question before the change order one , but again one of the  answer saying change to contract sum is material+labor+profit which seem to fit into 3.8.2.2 . but the answer is wrong .

    I am not sure this is just an error or I misunderstood the contract. ( below a is the correct answer)

    1
    Comment actions Permalink
  • Avatar
    Kun Wu

    604 and 603 are a little different.

    For question 604, the GC already took the labor, overhead and profit into account when sending the bid, because he know there was a desk to install, whether cheap or expensive. So the cost of the desk itself wont affect GC's labor, overhead and profit.

    I will let others to answer for question 603, but I tend to say C is correct.

    0
    Comment actions Permalink
  • Avatar
    Philip Li

    Anyone got a solution to 603?

    3.8.2.2 allowances does not include site, labor, installation costs, overhead, profit and other expenses and shall be included in the contract sum.

    Wouldn't it be 7767.25-5000?

    0
    Comment actions Permalink
  • Avatar
    Matthew Mead

    For 603, how are you able to answer if you don’t know what the original construct sum was? The only way A could be correct is if you disregarded the language in the A201 about allowances. If labor is included in the allowance then you’d also have to include the $300 to install on site which would make the answer B. Something is off here...

    0
    Comment actions Permalink
  • Avatar
    Gregory Brown

    Not completely sure about this, however after reading through the question #603 two times step-by-step ~ (likely not what would happen in the actual exam scenario) I believe the answer would be (D).

    Here is what I came up with:

    1. The Allowance = $5000, (this is an allowance by definition "each contractor instructed to include") it is assume to be a component of the total cost of the project w/o/ question.
    2. The invoice from Meridian Millwork Company = $7767.25 as provided (does not include contractors overhead and profit rate of 15%). So, this will need to be applied at the end.
    3. The question goes on to state that two workers worked to install the custom desk three hours at a rate of $50.00 / hour = (2 workers) x (($50 / hr)/3 hrs) = $300.00
    4. Finally the total = $7767.25 + $300.00 = $8067.25 + (15% overhead & profit) = $9277.33 - $5000 = $4277.34 ~ (answer D).

    Ballast sometimes as you are aware does have questions that are more detailed (intentionally designed to help). This question actually could show up on the CE exam. IF it did and I didn't have time to give it enough thought I'd either flag it, or guess and move on. Hope this helps.

     

    0
    Comment actions Permalink
  • Avatar
    Gang Chen

    David (Kaplan) is correct, allowance is a completely different concept, and does not apply to question 604.

    The two parties in the contract have to be treated equally, so the overhead and profit has to be included, regardless of the change orders: If you are including the overhead and profit when a change order increases the contract sum, then you have to do the same when a change order decreases the contract sum. So, the answer should be C for question 604.

    Ballast may have made a mistake here. We are all human and we all make mistakes.

    Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)

    1
    Comment actions Permalink
  • Avatar
    Gang Chen (Edited )

    Yes,  a change order ALWAYS includes overhead and profit. 

    Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)

    1
    Comment actions Permalink
  • Avatar
    Jinliang Chen

    Hi Gang, thank you for your clarification! It helped a lot. I just erased my answer since they were so misleading. Btw, I just got a likely pass today for CE. Start to dig more comments from you on PA!

    0
    Comment actions Permalink
  • Avatar
    Gang Chen

    I am glad it was helpful. Congratulations on the likely pass for CE!

    Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)

    0
    Comment actions Permalink

Please sign in to leave a comment.

Powered by Zendesk