Field Reports part of Contract Documents?

Comments

2 comments

  • Avatar
    Gang Chen

    It is confusing. If the language is “Moisture resistant gypsum board is missing and not installed per the construction documents…”, then a change order can be denied.

    Gang Chen, Author, AIA, LEED AP BD+C (GreenExamEducation.com)

    0
    Comment actions Permalink
  • Avatar
    Rebekka O'Melia

    If a contractor did poor work, or didn't protect the work and it got wet or damaged, they need to replace it.  There's no change order because it's not additional work or an upgrade.

    Hope this helps!

    Rebekka O'Melia, R.A., NCARB, B. Arch, M. Ed, NOMA, Step UP ARE 5.0 Courses