    Not at all. Please see AIA G710-2017: Architect's Supplemental Instructions 'The GC shall carry out the work with the following WITHOUT CHANGE IN CONTRACT SUM OR CONTRACT TIME.'

    The RFP is used to SOLICIT A CHANGE ORDER, and the proposal includes either or both: cost and time.

    It is a basis for the architect to prepare a Change Order to the contract, not an ASI