Public vs private project in considering alternates.

Comments

3 comments

  • Avatar
    Haytham Abdelrahman Abdelall

    If the question says : Public Projects w/o mentioning which alternate the O prefers, it means Base Bid and the Sum for the 3 bids, the lowest bid will be M. In the above question it's clearly stated that O prefers Alt 2, other Alt is out of the thought.

    0
    Comment actions Permalink
  • Avatar
    Yuan Ma

    Hi Haytham, 

    Thank you for the information. In the public project, is the owner allowed to pick any alternates in any order?

    0
    Comment actions Permalink
  • Avatar
    Haytham Abdelrahman Abdelall

    Alternates are used to reduce the contract sum for items, the price and quantity are know. I think yes the owner has the right to do so as there was no previous comment to include any. 

    0
    Comment actions Permalink