Construction contract time VS. Architect contract time

Comments

2 comments

  • Avatar
    Haytham Abdelrahman Abdelall

    You're correct, as per A 201 SEC # 8.1.1 & 8.1.2 

    Unless otherwise provided, Contract Time is the period of time, including authorized adjustments, allotted in the Contract Documents for Substantial Completion of the Work.

    The date of commencement of the Work is the date established in the Agreement.

    For the Arch, the end of Architect’s CCA services at the final completion w the final application of payment ( usually after the final inspection for final completion) however, Arch duties will end 1 year after substantial completion.

    0
    Comment actions Permalink
  • Avatar
    Yuan Ma

    Hi Haytham, thank you for confirming. 

    0
    Comment actions Permalink